Project Overview:

Denver International Airport is seeking a private sector partner to embrace the airport’s strategic vision and determine the optimal redevelopment scenario for the Great Hall Project that meets the following primary objectives:
  • ​Relocate TSA entirely from level 5 and open the Great Hall to new retail opportunities.
  • Reconfigure Level 6 to increase passenger processing efficiency.​​​


DIA’s Pursuit Timetable for Remainder of Process​
Submission of Final Response May 18, 2016
Selection of Preferred Proponent​ June 2016​
NTP for Predevelopment Agreement September 2016
Indicative Commercial Close Februar​y 2017
Indicative Financial Close May 2017
Target Construction Start Q2 2017
Target Construction Complete Q4 2019