PCL’s scope included the installation of civil, structural steel, piping, mechanical equipment, electrical and instrumentation, insulation, heat tracing, and paint. PCL worked over 35,823 direct-hire hours and oversaw an additional 18,619 trade contractor hours over a span of eight months. The direct scope progress base included 28,472 hours for the installation of the following commodities: 8,264 cubic yards of excavation/backfill, 340 cubic yards of concrete, 31 tons of structural steel, 14 pieces of mechanical equipment, 8,100 linear feet of piping, 52,738 linear feet of conduit, and 56,000 linear feet of cable.