Current Progress
(as of June 10, 2009) PCL has turned over 9 of 15 suites. The remaining 6 suites are currently unsold and are undergoing changes. The building envelope is watertight. Stone to the exterior is approximately 85% complete. All stone work is scheduled to be complete by the end of July 2009. Exterior balcony work (soffits, fascias, railing and pavers) in ongoing on levels 11 – 21. Two of the 5 elevators have been commissioned and turned over. Two more cars will be complete by the end of June with the last car being completed in July 2009. Project Description
Visit http://www.155cumberland.com/ to view the condominium website.
|