Current Progress

Safety

In the month of February, there were two Medical Aids and eight First Aid injuires; two of the First Aid injuries were to PCL workers.

PCL employees continue to be LTI free since the beginning of the project (1161 days).

Envelope

The glazing to the handrails is complete; deficiencies are near completion.

Electrical

Final device and cable commissioning for nurse call, fire alarm and security is nearing completion.

Kitchen/Cafeteria

Walk-in coolers, freezers and refrigeration equipment final start-ups have been completed.  Fire suppression testing and verification was completed in February.

Interiors

Interior partitions are effectively complete, with just deficiency clean-up being worked on. Painting is essentially complete, stairwell handrails and nosings are underway, as the final paint prior to final cleaning throughout the building.  Flooring is essentially complete, the focus continues on deficiency clean-up and installing tactile warning strips in stairwells.

Patient Lift

Patient lift motor installation is complete.

On-Site Works

The structured lawn for the fire access way and medical gas storage is complete.  The fabric to the canopy on the palliative care balcony has been installed.

Off-Site Works

The Highland Park area and Marshall Road frontage planting is complete, with the exception of the top of the sierra wall which will be completed when the weather permits.  The bus pad on Marshall Road has been completed.

Project Description

The Abbotsford Regional Hospital and Cancer Centre is the first Public-Private Partnership (P3) Hospital to be built in British Columbia. Construction on the facility started in 2005 and is scheduled to be complete in Spring 2008.

The Hospital will have a total area of approximately 63,000 square metres distributed over five levels. It is situated on approximately 10 hectares of land in Abbotsford, British Columbia, bound by the Trans-Canada Highway to the south, Gladwin Road to the west and Marshall Road to the north.

This 300-bed, state-of-the-art facility will be three times larger than the current acute care hospital it is replacing. It will provide enhanced and specialized health services to more than 150,000 people in the Abbotsford area and up to 330,000 in the Fraser Valley.A cancer treatment centre, which will be run by the BC Cancer Agency, has been integrated into the hospital's design, and will provide diagnosis and treatments such as MRIs, radiation and chemotherapy, kidney dialysis and specialized surgeries previously only available by driving to Surrey, BC.

Access Health Abbotsford (AHA) is the P3 consortium selected for the design, construction, financing and maintenance of this facility. PCL Constructors Westcoast Inc. is the consortium partner responsible for design and construction. Each partner in the consortium contributes expertise from their specialized business practices to deliver this project through an innovative P3 arrangement in collaboration with Partnerships BC.


AHA is made up of the following partners:

    •  John Laing Investments Abbotsford Ltd.   – Overall AHA Project Management

    •  ABN AMRO Bank N.V. – Finance and Development
    •  PCL Constructors Westcoast Inc. – Design-Build Contractor

    •  MCM/Silver Thomas Hanley  – Design Services

    •  Johnson Controls and Sodexho – Facility Management Services

 

 
Contact

Contact Project

Phone: (604) 851-5649
Fax: (604) 851-6226

Owner

Prime Consultant