EXPEDIENT CONSTRUCTION is dependent on effective planning and scheduling.

During the estimating stage, we establish base line plans and schedules to provide clients with the interim reports required to make informed, low risk decisions. At the same time, our advanced project management tools give our project teams what they need to maintain disciplined project control. Our clients benefit from our “save-time-save-money” process, as we share best practices and technology through an in-house Scheduling User Group that includes representatives from the entire PCL family of companies.

Below, our clients and other construction partners talk about the leadership of the PCL family of companies:

Hillsboro Inlet Bascule Bridge Rehab
Hillsboro Inlet Bascule Bridge Rehab
After receiving this contract from FDOT District 4, PCL was asked to speed up the schedule to reduce impacts on the neighboring community and the travelling public. Local opposition to the project almost caused FDOT to cancel the contract. PCL put together a proposal for schedule reduction that addressed the stakeholders' concerns. The bridge was repaired expeditiously and FDOT eventually rewarded PCL with an early completion bonus.
Royal Park Temporary Bascule D/B Bridge
Royal Park Temporary Bascule D/B Bridge
The PCL team had just over one month to prepare a technical proposal, conceptual design and pricing for fast-track design and construction of a temporary bascule bridge. PCL received a early completion bonus for on time completion of a very aggressive 12-month construction schedule on this project. The project won the 2001 National Design Build Award from the Design Build Institute of America.

Suncoast Parkway Completion
Suncoast Parkway Completion
The St. Paul Surety Company asked PCL to complete this project after another contractor was removed from the contract. PCL mobilized on to the project within one week and had 40 men working within three weeks. PCL immediately redesigned the MOT phasing which expedited the opening of the Veteran's Expressway and the completion of the project. The project won the "2001 Major Interstate Award" from the Florida Department of Transportation.


 

 