Crypto.com Arena is one of the most active multipurpose venues in the world, hosting professional sports, concerts and globally televised events year‑round. To modernize the facility while maintaining uninterrupted operations, the client required a highly strategic renovation approach that balanced speed, safety and flexibility.

PCL delivered a four‑phase renovation program over five years, carefully sequencing work to avoid disruption to major events. Drawing on its deep institutional knowledge from constructing the original arena, PCL served as a trusted long‑term partner, coordinating closely with arena operations and stakeholders to execute fast‑track renovations while the venue remained fully operational.

Phase 1: This phase focused on upgrading high‑traffic public and team spaces, including concourse‑level flooring, ceilings, finishes, washrooms, dining areas and team locker rooms. The scope also included installation of state‑of‑the‑art LED screens and ribbon boards. In total, 94,205 square feet were renovated, including the Chairman’s Club (now known as the Delta SKY360° Club), the Impact Sports Bar & Grill, and exclusive suites.

Phase 2: This phase expanded premium offerings with the construction of eight new VIP suites—four accessed from the Main Concourse and four from the Event Level, providing private access to the seating bowl. The Upper Concourse was refreshed with new tile, paint, restroom fixtures, partitions, and signage and seating layouts were reconfigured to increase seat count. 

Phase 3: This phase introduced a refresh of the Main Concourse and Suite Level A Clubs, along with the creation of a new City View Terrace entertainment space, further elevating the fan and premium guest experience.

Phase 4: The final renovation phase involved the demolition and complete rebuild of the NBA and NHL visitor locker rooms. Executed entirely during the offseason, this phase required disciplined staffing coordination, cost control and sequencing. PCL led the procurement and integration of specialty finishes, advanced AV systems and league‑compliant player amenities, working in close alignment with arena operations to preserve full event readiness while meeting NBA and NHL standards. 

PCL completed all four phases on fast-tracked schedules, performing much of the work at night to avoid any impact on games or events.

  • Delivery Approach: Four‑phase renovation program over five years
  • Key Upgrades: 

    • Concourse finishes, restrooms, and in‑arena dining
    • Premium clubs, suite levels, and VIP suites
    • LED screens and ribbon boards
    • City View Terrace entertainment space
    • NBA and NHL visitor locker rooms
  • Construction Strategy: 

    • Night work and restricted hours
    • Fast‑track delivery within active event schedules
    • Continuous coordination with arena operations
PCL’s leadership across multiple renovation phases reflects a long‑standing client relationship and an ongoing commitment to preserving and evolving one of North America’s most recognizable sports and entertainment venues.
 